Excavation of the new stormwater detention pond is almost complete and the relocated segment of Sartartria Road is now open to traffic.
Currently, more than 200,000 cubic yards of material have been excavated to create the new pond.
The final phase of construction requires the abandonment and removal of Sartartria Road on the south side of the new pond. As soon as the road can be removed, the new detention pond will be connected to Ellis Creek.
In August and September, dump trucks will continue to haul material away from the site. Please remain aware of construction traffic when traveling near Williams Landing Dr., Sandhill Dr., and Sartartria Rd.
The Stormwater Detention Project is anticipated to be complete within the next three months.