December 2023
Construction of the new Stormwater Pump Station has been delayed and is currently scheduled to be complete in March 2024. The Pump Station structure and building are complete, but the electric pumps and motor control equipment cannot be installed until CenterPoint provides electricity to the site. The installation of pumps and motor controls has remained a critical construction activity throughout the project and the lack of power will continue to delay their completion.
The LID 7 Board of Directors thanks all the residents of New Territory for their support and patience as this critical flood mitigation project proceeds. For questions regarding the project, please reach out to the District via the “Contact Us” page on the FBCLID 7 website.