The Texas Water Development Board (TWDB) recently approved the plans for the FBCLID 7 Stormwater Detention Project. When complete the project will add 115 acre-feet, or 37 million gallons, of additional storage to the FBCLID 7 drainage system. In August 2022, TWDB awarded FBCLID 7 a $324,000 grant and a 0% loan of $10,486,000 to pay for construction of the Stormwater Detention Project. Now that the plans are approved, the public bidding process has started. FBCLID 7 has acquired all property needed to construct the detention pond, and utilities are currently being relocated. Construction is scheduled to start in Fall 2023 and be complete before Summer 2024.